At ValidExamDumps, we consistently monitor updates to the The Open Group OG0-023 exam questions by The Open Group. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the The Open Group ArchiMate 2 Combined Part 1 and 2 ination exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by The Open Group in their The Open Group OG0-023 exam. These outdated questions lead to customers failing their The Open Group ArchiMate 2 Combined Part 1 and 2 ination exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the The Open Group OG0-023 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

Consider the following diagram, which shows a relationship between two business objects:

Which of the following best describes the relationship shown in the diagram between Insurance Policy and Insured Individuals?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

Which of the following phases of the TOGAF ADM correspond most closely to the ArchiMate Motivation Extension?

Show Answer Hide Answer
Correct Answer: A

Question No. 3

Consider the following example view:

Which of the following best describes how this view could be used?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

Consider the following diagram:

Which of the following best describes what this diagram represents?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Scenario

Please read this scenario prior to answering the question

ArchiSurance senior management, board members, customers and major stockholders have long been concerned about disaster resiliency in light of the company's heavy reliance on a single data center. The data center is located in an area that is prone to flooding and earthquakes, according to expert assessments done by consultants retained for this purpose. In addition, the data center is located under a busy cafeteria, and water occasionally leaks through its ceiling.

To adoress these problems, ArchiSurance has developed a plan to move from its current data center to a pair of ready-to-use data centers in separate cities. The data center move is designed to reduce the risk of business interruption, reduce both planned and unplanned downtime for critical applications, and reassure ArchiSurance stakeholders. However, a number of limitations make theplanned transition to the new data centers particularly challenging. A number of critical ArchiSurance applications cannot be offline for more than an hour, and any downtime for these application must only occur in certain four-hour windows each weekend. Also, the move cannot occur during quarterly or year-end closing periods in order to avoid interrupting critical processing. Fulfillment of these specific type of requirements will reduce the risk of business interruption from the data center move activities themselves.

ArchiSurance management has therefore planned a multi-phase data center transformation program. All of the activities in each phase are necessary to ensure a progression of stable and fully functional data center configurations. The first phase consists of detailed scheduling and planning to produce a comprehensive transformation plan that meets ArchiSurance timing and scheduling requirements During the second phase, ArchiSurance is to contract for the hardware and software required for the new datacenters,as well for refunds for the hardware and software to be returned from the current data center once it is shut down. During the third phase, the new data centers are to be set up, and the new hardware and software are to be tested in parallel with what is already in production. The actual transition between the old and new data centers occurs in the fourth phase, and the fifth phase involves shutting down and dismantling the old data center, and returning its hardware and software for contracted refunds. Phases two through five are each to be initiated when specific conditions are met in the previous phase.

Refer to the Scenario

The newly hired program manager for data center transformation has asked you to describe the program implementation plan. You must express each of the plan phases as a separate work package with specific deliverables. You must also show the relationships between phases along with how each phase contributes to a particular stable data center state.

Which answer provides the best description?

Show Answer Hide Answer
Correct Answer: B