Free Scrum PSD Exam Actual Questions

The questions for PSD were last updated On Dec 19, 2024

Question No. 1

What activities would a Product Owner typically undertake in the phase between the end of the current sprint and the start of the next sprint?

Show Answer Hide Answer
Correct Answer: D

There is no time in between sprints, so there cannot be activities.


Question No. 2

Which of the following best describe continuous integration?

Show Answer Hide Answer
Correct Answer: D

Question No. 3

Who is responsible for the system architecture of a product developed using Scrum?

Show Answer Hide Answer
Correct Answer: D

Scrum doesn't know any other role than developer. The developers are cross-functional and have all the skills needed to create a usable increment. They are doing the work and responsible for the architecture.


Question No. 4

What are the developers responsible for? (choose two)

Show Answer Hide Answer
Correct Answer: A, C

They are concerned with everything that needs to happen to create a working increment. And they are self-managing, so resolving conflicts is something they should arrange as well.


Question No. 5

What is the purpose of a sprint retrospective? Choose two

Show Answer Hide Answer
Correct Answer: A

In the scrum guide it says: 'The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness.'