Free SAP C_TS422_2023 Exam Actual Questions

The questions for C_TS422_2023 were last updated On Nov 16, 2024

Question No. 1

What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: A, C

Question No. 3

Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Show Answer Hide Answer
Correct Answer: A

Question No. 4

Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: B, D

Question No. 5

Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: A, B