Free SAP C_TS422_1909 Exam Actual Questions

The questions for C_TS422_1909 were last updated On Nov 4, 2024

Question No. 1

What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.

Show Answer Hide Answer
Correct Answer: A, D, E

Question No. 2

Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: C, D

Question No. 3

Which of the following is a valid sequence of the main activities in product on order processing?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

When do you use variant bills of materials (BOMB)?

Show Answer Hide Answer
Correct Answer: C

Question No. 5

Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.

Show Answer Hide Answer
Correct Answer: B, C, E