Free SAP C_TS412_1909 Exam Actual Questions

The questions for C_TS412_1909 were last updated On Nov 7, 2024

Question No. 1

Cost & Budget

You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation.,

and have entered the quotation ...

What is the typical sequence for the following business transactions and document.

Show Answer Hide Answer
Correct Answer: D

Question No. 2

What is the reason for assigning billing plans in customer projects?

Show Answer Hide Answer
Correct Answer: B

Question No. 3

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

Show Answer Hide Answer
Correct Answer: B

Question No. 4

A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

Show Answer Hide Answer
Correct Answer: D

Question No. 5

Material

You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?

Note : there are 2 correct answers for this question.

Show Answer Hide Answer
Correct Answer: A, B