Free SAP C_S4CPB_2408 Exam Actual Questions

The questions for C_S4CPB_2408 were last updated On Nov 20, 2024

Question No. 2

Which of the following activities are completed in the Realize phase of the SAP Activate Methodology? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Question No. 3

Based on the SAP Activate methodology, which activities must you perform in the Explore phase? Note:

There are 2 correct answers to this question.

Show Answer Hide Answer
Question No. 4

You have assigned a deployment target in SAP Central Business Configuration, but have not yet completed the Confirm Scoping milestone.

Which of the following tasks can you complete? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Question No. 5

Which activities does the consultant do before the first Fit-to-Standard workshop? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: A, C

Before the first Fit-to-Standard workshop, the consultant should do the following activities:

Deactivate scope items that are NOT part of the Statement of Work/Digital Discovery Assessment. This is to ensure that the Starter system reflects the agreed scope of the project and does not include any unnecessary or out-of-scope items.The consultant can use the Scope Item Management app to deactivate scope items1.

Review the integration requirements collected from the Digital Discovery Assessment. This is to understand the customer's integration needs and prepare for the integration topics that will be discussed in the Fit-to-Standard workshop.The consultant can use the Integration Solution Advisor tool to review the integration requirements and the recommended integration scenarios2.

The consultant should NOT do the following activities before the first Fit-to-Standard workshop:

Upload customer master data in the Starter system using migration templates. This is not required before the first Fit-to-Standard workshop, as the customer master data is not relevant for the process validation.The consultant should upload the customer master data in the Quality system after the Fit-to-Standard workshop, using the SAP S/4HANA Migration Cockpit3.

Evaluate the L2 Business-Driven Configuration Questionnaire responses. This is not required before the first Fit-to-Standard workshop, as the L2 Business-Driven Configuration Questionnaire is not available at this stage. The consultant should evaluate the L2 Business-Driven Configuration Questionnaire responses after the Fit-to-Standard workshop, using the SAP Activate Methodology.

Reference=

1:Scope Item Management App

2:Integration Solution Advisor Tool

3:SAP S/4HANA Migration Cockpit

: [SAP Activate Methodology]