Question No. 1

You change an active project baseline and save it. Then, the system creates a new baseline.

What are the statuses of the previous baseline and new baseline?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

An employee creates a shopping cart for a product. The purchase order is created automatically. When the product is delivered, the employee confirms its delivery.

Which one of the following accounts will be credited in the automatic posting from the goods receipt from the supplier?

Show Answer Hide Answer
Correct Answer: D

Question No. 3

Which of the following pricelists are delivered by SAP?

Note: There are 3 correct answers to this question.

Show Answer Hide Answer
Correct Answer: A, B, C

Question No. 4

What information from a statement of work is considered when creating a project?

Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: B, D

Question No. 5

For which of the following business objects can you create invoice schedules in SAP Business ByDesign?

Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: B, D