Free SAP C_ACTIVATE13 Exam Actual Questions

The questions for C_ACTIVATE13 were last updated On Nov 18, 2024

Question No. 1

What term is used for a ready-to-run SAP S/4HANA system with pre-built solution Documentation

Show Answer Hide Answer
Correct Answer: A

Question No. 2

Preliminary strategy developed by the customer to approach the project in a specific workstream

Show Answer Hide Answer
Correct Answer: C

Question No. 3

In which phase do you create "an ordered list of everything that is known to be needed in the Product?

Show Answer Hide Answer
Correct Answer: B

Question No. 4

According to the definition of done, which activity must be completed for each sprint?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path?

There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: B, C