Free PMI PMP Exam Actual Questions

The questions for PMP were last updated On Apr 16, 2025

At ValidExamDumps, we consistently monitor updates to the PMI PMP exam questions by PMI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PMI Project Management Professional (2024) exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI PMP exam. These outdated questions lead to customers failing their PMI Project Management Professional (2024) exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PMI PMP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

Show Answer Hide Answer
Correct Answer: A

According to the PMI-PBA guide, quality standards are the criteria that the project team uses to measure the quality of the product or service. Quality standards should be aligned with the customer's needs and expectations, and should be defined and agreed upon by the project team and the stakeholders. Quality standards should also be adaptable to the changing requirements and feedback in an agile environment. One of the agile principles is to deliver working software frequently, which implies that testing should be done early and continuously throughout the project lifecycle. Testing is not only a way to verify the quality of the product, but also a way to validate the value of the solution and elicit feedback from the customer. Therefore, the project manager should coach the team to determine the tools and techniques suitable for the project and ensure that testing is done early and continuously, as this will help the team deliver a high-quality product that meets the customer's needs and expectations.Reference:

PMI-PBA guide, Chapter 5: Planning the Business Analysis Approach, Section 5.2.3: Quality Standards, p. 115-116

PMI-PBA guide, Chapter 6: Traceability and Monitoring, Section 6.2.1: Testing, p. 141-142

PMI-PBA guide, Appendix A: Agile Principles and Practices, Section A.1: Agile Principles, p. 263

PMP Exam Study Guide, Chapter 8: Quality Management, Section 8.1: Plan Quality Management, p. 395-396

PMP Exam Study Guide, Chapter 8: Quality Management, Section 8.4: Control Quality, p. 413-414


Question No. 3

A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.

What should the project manager do next?

Show Answer Hide Answer
Question No. 4

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

Show Answer Hide Answer
Correct Answer: D

When a project manager identifies a risk with a high probability of occurring, the appropriate response is to monitor the risk closely. This involves asking the team to keep an eye on the risk and provide alerts if it becomes an issue. This approach is aligned with the proactive risk management practices advocated by PMI, where risks are continuously monitored and managed throughout the project lifecycle. It allows the project team to respond quickly to changes and implement risk response plans as necessary.


The PMBOK Guide -- Sixth Edition provides guidelines on risk management processes which include monitoring risks.It emphasizes the importance of keeping track of identified risks, monitoring residual risks, and reviewing the execution of risk responses while evaluating their effectiveness throughout the project lifecycle1.

The Practice Standard for Project Risk Management by PMI also supports this approach, detailing how monitoring and controlling risks is a critical part of the risk management process2.

Additionally, the PMP Exam Content Outline from PMI outlines the tasks associated with monitoring risks, which includes implementing risk response plans, tracking identified risks, and evaluating risk process effectiveness over the project's duration3.

Question No. 5

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

Show Answer Hide Answer