Free PMI PMI-SP Exam Actual Questions

The questions for PMI-SP were last updated On Apr 21, 2025

At ValidExamDumps, we consistently monitor updates to the PMI-SP exam questions by PMI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PMI Scheduling Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI-SP exam. These outdated questions lead to customers failing their PMI Scheduling Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PMI-SP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

Which of the following group activity techniques allows a large number of ideas to be sorted into groups for review and analysis?

Show Answer Hide Answer
Correct Answer: D

The various group creativity techniques are as follows:

Brainstorming: It is a technique used to generate and collect multiple ideas related to the project

and product requirements.

Nominal group technique: It is a technique used to enhance brainstorming with a voting process

used to rank the most useful ideas for

further brainstorming or prioritization.

Delphi technique: It is a techniques used to identify potential risk. In this technique, the responses

are gathered via a questionnaire

from different experts and their inputs are organized according to their contents.

Idea/mind mapping: It is a technique used to map the ideas generated by brainstorming to reflect

the commonality and differences in

understanding and generating new ideas.

Affinity diagram: It is a technique used to allow a large number of ideas to be sorted into groups for

review and analysis.


Question No. 2

You are the project manager for your organization. You are working with your project team to define the project network diagram. Several of the activities in the project schedule appear to have external constraints. Who among the following determines which dependencies are external to the project?

Show Answer Hide Answer
Correct Answer: D

The project management team defines which activities are external to the project.

An external dependency is any nonproject activity that is external to the project but has a direct

impact on the project activities. An external

dependency may be an inspector or any agency that may have to give prior approval before the

project can move forward. These

dependencies are external to the organization and are determined by the project management team

to find which dependencies are external

all through the process of sequencing the activities.

Answer option C is incorrect. The project manager may be part of the project management team,

but this is not the best choice.

Answer option A is incorrect. The project team does not define this relationship.

Answer option B is incorrect. The project sponsor would not define the external dependencies.


Question No. 3

You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. What is the planned value for this project?

Show Answer Hide Answer
Correct Answer: A

The planned value is the percent complete that the project should have done. In this instance, it is:

Planned value = 45% of $1,258,456

=$566,305

Answer option B is incorrect. This is the project budget.

Answer option D is incorrect. $503,382 is the earned value for this project.

Answer option C is incorrect. -$54,044 is the variance at completion for your project.


Question No. 4

You work as a project manager for Blue Well Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

Show Answer Hide Answer
Correct Answer: D

The various phases of the decision making process are as follows:

Problem definition: This phase explores, clarifies and defines the problem.

Problem solution generation: This phase draws out the new idea generating process by

brainstorming multiple solutions and rejecting

premature decisions.

Ideas to action: This phase defines the evaluation criteria, rate pros and cons of alternatives and

helps in selecting the best solution.

Solution action planning: This phase involves key participants to gain acceptance and commitment to

make the solution work.

Solution evaluation planning: This phase performs the post implementation analysis, evaluations and

lessons learned.

Evaluation of the outcome and process: This phase evaluates how well the problem was solved or

project goals were achieved.


Question No. 5

You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

Show Answer Hide Answer
Correct Answer: D

The consultant is an example of expert judgment, as he is helping you and the project team to create the project elements. Expert judgment is a technique based on a set of criteria that has been acquired in a specific knowledge area or product area. It is obtained when the project manager or project team requires specialized knowledge that they do not possess. Expert judgment involves people most familiar with the work of creating estimates. Preferably, the project team member who will be doing the task should complete the estimates. Expert judgment is applied when performing administrative closure activities, and experts should ensure the project or phase closure is performed to the appropriate standards. Answer option A is incorrect. The consultant may be considered a direct expense because the fees can only be assigned to your project work, but this is not the best choice for the question. Answer option B is incorrect. An external requirement is not a valid choice for this question. Answer option C is incorrect. A temporary resource is not a valid project management term.