Free PMI PMI-RMP Exam Actual Questions

The questions for PMI-RMP were last updated On Mar 27, 2025

At ValidExamDumps, we consistently monitor updates to the PMI-RMP exam questions by PMI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PMI Risk Management Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI-RMP exam. These outdated questions lead to customers failing their PMI Risk Management Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PMI-RMP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Show Answer Hide Answer
Correct Answer: C

The project risk manager should generate reports to assess and communicate the project risk level to stakeholders. This helps in making informed decisions and taking appropriate actions to manage risks effectively.

The project risk manager should quantify the risk exposure that exceeds project contingency, as this will help to determine the amount of management reserve needed to cover the potential cost overruns or schedule delays. The project risk manager should also communicate this information to the project manager and other relevant stakeholders, and update the risk management plan accordingly.Reference:The Standard for Risk Management in Portfolios, Programs, and Projects, page 80; PMBOK Guide, 6th edition, page 407.


Question No. 2

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Show Answer Hide Answer
Correct Answer: C

When a new risk manager is assigned to an ongoing project, their first step should be to review the existing risk management plan to understand the current policies, practices, and strategies in place.

The new risk manager should first review the policies and practices that are outlined in the risk management plan, as this is the document that describes how risk management will be performed on the project. The risk management plan defines the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance structure for the project. The new risk manager should familiarize themselves with the risk management plan to understand the project environment and the expectations and requirements for risk management. The other options are not the first actions that the new risk manager should take. Reviewing potential next steps with the project team is a good practice, but it should be done after reviewing the risk management plan to ensure alignment and consistency. Reviewing the scope of work to determine the prescribed project methodology is not directly related to risk management, and it may not provide sufficient information about the project environment and the risk management approach. Reviewing the contract and determining the resources and project funding is part of the project initiation process, and it may not reflect the current status and issues of the project.Reference:2,3,4


Question No. 3

A project team is performing the last status meeting session of a projects iteration. What should the risk manager do before starting the next iteration?

Show Answer Hide Answer
Correct Answer: B, B

Question No. 4

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.

What should the team perform in this scenario?

Show Answer Hide Answer
Correct Answer: A

Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. (Reference: PMBOK Guide, 6th Edition, p. 423)

The team should perform quantitative risk analysis, which is the process of numerically analyzing the effect of identified risks on overall project objectives. Quantitative risk analysis can help the team to establish the minimum acceptable level of exposure and impact for each risk, as well as the maximum level of exposure before escalation. Quantitative risk analysis can also provide probabilistic estimates of project outcomes, such as cost and schedule, and support risk prioritization and decision making.Reference:PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition, 2017, p. 399; PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 69.


Question No. 5

An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.

What should the risk management expert recommend the agency do first to identify risks and develop the handbook?

Show Answer Hide Answer
Correct Answer: D

According to the PMBOK Guide1, risk identification is the process of determining which risks may affect the project and documenting their characteristics. It involves the use of various techniques to gather information from different sources and perspectives, such as stakeholders, experts, historical data, assumptions, and environmental factors. Some of the common techniques for risk identification are meetings, facilitated workshops, interviews, brainstorming, checklists, questionnaires, SWOT analysis, and root cause analysis. These techniques help to elicit the knowledge and opinions of the participants, and to generate a comprehensive list of potential risks that can be further analyzed and prioritized. In this case, the risk management expert should recommend the agency to conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks and develop the handbook. This will help to understand the context and objectives of the agency, the expectations and concerns of the farmers and landlords, the challenges and opportunities in the agriculture sector, and the possible sources and impacts of uncertainty. The risk management expert can then use the information gathered from these techniques to create a risk register and a risk management plan, which can form the basis of the handbook.This is part of the Identify Risks process in the PMBOK Guide1.Reference:1: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition

Engaging stakeholders through meetings, workshops, and interviews is crucial for risk identification, as it allows the agency to gather diverse perspectives and insights on potential risks. This approach is more effective than relying solely on standard tools or hiring an expert.