Free PMI PMI-ACP Exam Actual Questions

The questions for PMI-ACP were last updated On Mar 25, 2025

At ValidExamDumps, we consistently monitor updates to the PMI-ACP exam questions by PMI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PMI Agile Certified Practitioner exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI-ACP exam. These outdated questions lead to customers failing their PMI Agile Certified Practitioner exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PMI-ACP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

A project sponsor is upset that an enhancement will be unavailable until next year. What should the product owner do?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.

What should the team do?

Show Answer Hide Answer
Correct Answer: C

Question No. 3

A team is creating a highly marketed, time-sensitive product. The agile coach is concerned that anything other than exceptional quality will result in bad publicity for the company.

What should the agile coach ensure that developers do?

Show Answer Hide Answer
Correct Answer: D

Question No. 4

After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.

If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?

Show Answer Hide Answer
Correct Answer: C