Free PMI PfMP Exam Actual Questions

The questions for PfMP were last updated On Nov 17, 2024

Question No. 1

One of the major resources on your portfolio is needed by two of the components at the same time. This resource has high technical knowledge and is aware of all the business needs. Which of the following tools and techniques can you use in order to solve this issue?

Show Answer Hide Answer
Correct Answer: A

Question No. 2

After the second shutdown of the Government, your Agency Administrator realized that some essential programs had to continue even during the shutdown, some existing work along with some programs and projects in the pipeline perhaps were not needed, and resources may require reallocation. This example shows the:

Show Answer Hide Answer
Correct Answer: B

Question No. 3

Assume you are a functional manager in your medical device company in research and development. Your scientists have determined a new product that will be a breakthrough for the company, and you want to serve as the sponsor for this component and present it to your Portfolio Review Board. You will need resources from other parts of the company to commercialize it. As you prepare your proposal you are following the key descriptors set up by the portfolio staff and will include:

Show Answer Hide Answer
Correct Answer: D

Question No. 4

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. The Portfolio Risk Management Plan is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding its purpose and focus?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Moving from project management to program management and now being appointed as the first portfolio manager in your cyber warfare company, you know you always wondered what happened to the various reports you had to prepare, and the metrics you had to collect. You are working now to determine critical metrics for portfolio management and decided to involve as many people as possible through questionnaires and surveys. You also held some focus groups. The purpose is to:

Show Answer Hide Answer
Correct Answer: B