Free PMI CAPM Exam Actual Questions

The questions for CAPM were last updated On Feb 19, 2025

At ValidExamDumps, we consistently monitor updates to the PMI CAPM exam questions by PMI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PMI Certified Associate in Project Management exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI CAPM exam. These outdated questions lead to customers failing their PMI Certified Associate in Project Management exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PMI CAPM exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

The project manager is looking at a precedence diagram.... the duration of this task?

The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

What is the outcome of the duration of this task'?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

A tool or technique used in the Control Procurements process is:

Show Answer Hide Answer
Correct Answer: B

Question No. 3

What communication methods would a project manager use for overall effective project communication?

Show Answer Hide Answer
Correct Answer: B

Question No. 4

An input to the Plan Cost Management process is:

Show Answer Hide Answer
Correct Answer: C

Question No. 5

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Show Answer Hide Answer
Correct Answer: B