Free Oracle 1Z0-1077-22 Exam Actual Questions

The questions for 1Z0-1077-22 were last updated On Nov 21, 2024

Question No. 1

Your customer wants to include externally managed manufacturing supplies in Global Order Promising results. What are the four steps that you perform to meet this requirement?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

What is the configuration required to automatically calculate the Jeopardy Score and priority when an orchestration process is planned or re-planned?

Show Answer Hide Answer
Correct Answer: D

You can enable the Replan Instantly feature when you define an orchestration process. It replans the orchestration process immediately after this process completes the orchestration process step, and then displays the revised order data according to the replanning work that it does. It is recommended that you use Replan Instantly only for high priority sales orders, or with sales orders that include a jeopardy threshold of less than one day. For performance reasons, it is recommended that you do not use it with an orchestration process step that is long or complex. If Replan Instantly does not contain a check mark, then Order Management updates the planning data only during the scheduled replanning.

https://docs.oracle.com/en/cloud/saas/supply-chain-management/r13-update17d/faiom/setting-up-orchestration-processes.html#FAIOM211469


Question No. 3

Your customer is concerned about not having access to schedule orders and check availability when the Global Order Promising server is down. Which two statements are true? (Choose two.)

Show Answer Hide Answer
Correct Answer: A, B

Question No. 4

Your company has a cost of change policy that changes a customer when the order is allocated, with no changes allowed after the goods are staged.

Which fulfillment status will trigger compensation and impose charges on the customer when the sales order quantity is changed?

Show Answer Hide Answer
Question No. 5

Identify three ongoing maintenance tasks that a user is required to execute from the Order Management Work Area after the Order Management Implementation is completed. (Choose three.)

Show Answer Hide Answer
Correct Answer: A, B, C