Free Oracle 1Z0-1075-24 Exam Actual Questions

The questions for 1Z0-1075-24 were last updated On Dec 20, 2024

Question No. 1

Which three types of item quantities are displayed on the Work Order History tab?

Show Answer Hide Answer
Correct Answer: A, B, C

The Work Order History tab in Oracle Manufacturing Cloud provides a summary of different item quantities related to the lifecycle of a work order. The following quantities are displayed:

In Process: This shows the quantity of items currently being processed in the production cycle.

Scrapped: This quantity reflects the number of items that have been discarded due to defects or other issues during the production process.

Completed: This quantity shows the number of items that have successfully been completed in the work order.

Incorrect options:

Remaining: The system does not specifically display a 'Remaining' quantity on the Work Order History tab.

Total: The total quantity is not shown as a standalone metric in the Work Order History tab but is implied by other metrics.


Question No. 2

Your client is planning to override the Plant Production Calendar with One or More Date-Effective Work Center Calendars. You need to explain the consideration when using the Override the Plant Production Calendar with One or More Date-Effective Work Center Calendars feature.

Which three statements are true when overriding the production calendar?

Show Answer Hide Answer
Correct Answer: A, C, D

Overriding the plant production calendar with date-effective work center calendars provides flexibility in scheduling specific work centers with different operating hours. However, certain aspects of production planning and execution remain tied to the plant-level calendar. Here are the details:

Statement A: The Work Execution Work Area Infolets and Manage Production Exceptions page are based on the plant calendar and not on work center calendars -- Even when work centers have their own calendars, the high-level overview and exception reporting remain based on the plant calendar.

Statement C: Lead time calculation in days for an item remains based on the plant calendar -- Lead times are calculated using the plant calendar, regardless of work center-specific calendars, ensuring consistency in planning.

Statement D: Search actions in the Review Dispatch List page query operations based on the plant calendar shifts when multiple work centers are selected -- For consistency in dispatching, the system references the plant calendar when shift-based search parameters are used across multiple work centers.

Incorrect Statements:

Statement B: Date-effective ranges for work center calendars should not overlap for accuracy in scheduling.

Statement E: Supplier operations in outside processing generally rely on the plant calendar for consistency unless explicitly configured otherwise.


Question No. 3

In which three ways does Supply Chain Orchestration enrich supply requests with project details to support outside processing for a project-specific work order?

Show Answer Hide Answer
Correct Answer: B, D, E

Supply Chain Orchestration (SCO) plays a vital role in managing project-specific work orders, particularly for outside processing. Here's how it enriches supply requests with project details:

Statement B: Expenditure Item Date is set to the requested need-by date and Expenditure Organization is set to the manufacturing plant -- In project-specific work orders, Supply Chain Orchestration assigns the need-by date as the Expenditure Item Date. The Expenditure Organization is typically set to the manufacturing plant handling the work order.


Statement D: Supply Chain Orchestration initiates the creation of a requisition with the project details -- SCO automatically creates a requisition with all relevant project details, such as project number, task, and expenditure information. This ensures that the procurement process is aligned with the project's financial and material requirements.

Statement E: Expenditure Type is set to the expenditure type associated with the outside processing item -- In Oracle Cloud, expenditure types must align with the specific processing items. SCO ensures that the correct expenditure type is applied to the work order and subsequent requisitions.

Incorrect Statements:

Statement A: SCO does not initiate the creation of a purchase order without the work order. A work order is essential for processing the outside work, and its absence would disrupt the orchestration process.

Statement C: The Expenditure Item Date is not set to the receipt date but rather to the requested need-by date for proper alignment with project scheduling.

Question No. 4

Which statement is NOT true about cumulative lead time?

Show Answer Hide Answer
Correct Answer: D

Cumulative lead time is a key concept in Oracle Manufacturing Cloud, where it calculates the total time required to manufacture an item. The following points clarify the calculations:

Statement D is incorrect because cumulative lead time does not update the lead time percent at the operation level in the work definition. Instead, cumulative lead time focuses on rolling up the lead times of both make and buy items to provide an overall lead time for the entire production process.

Correct Statements:

Statement A: The system calculates cumulative manufacturing lead time by summing up the lead times of all make items in the production process.

Statement B: At the end of the cumulative lead time calculation process, it updates the lead time attributes of the item, specifically cumulative manufacturing and cumulative total lead times.

Statement C: Cumulative total lead time includes both make and buy item lead times, representing the complete production cycle from procurement to manufacturing.


Question No. 5

Your customer is a light assembly manufacturing company that doesn't require shop floor control. A Manufacturing Engineer wants to generate a work definition automatically for some items, and wants to eliminate the explicit maintenance of work definitions.

Which three steps must they perform and verify in the Work Definition area?

Show Answer Hide Answer
Correct Answer: A, B, E

In light assembly manufacturing environments where shop floor control is not required, a Manufacturing Engineer can automate the creation of work definitions to streamline production processes. The following steps must be performed and verified:

Select a resource to be used in automatic work definition by enabling the Default attribute. This ensures that the system can automatically assign resources to the work definition without manual intervention.

Ensure the predefined work definition name ORA_MAIN is active, as this serves as the template for automatically generating work definitions in the system.

Select a standard operation for use in automatic work definition, also by enabling the Default attribute. This ensures that the system knows which operations to include in the work definitions.

Incorrect steps:

C: Secondary item structure is not relevant for automatic work definitions.

D: There can be multiple default operations, so it's not necessary to limit it to one.