Free Oracle 1Z0-1075-22 Exam Actual Questions

The questions for 1Z0-1075-22 were last updated On Nov 3, 2024

Question No. 1

Your customer has completed the required setup steps for automatic work definition. Identify the option that shows the navigation steps needed to create an automatic work definition.

Show Answer Hide Answer
Correct Answer: C

Question No. 2

In what three ways can you set the overcompletion tolerance for a subcomponent yield, so the job order can report the excess production completion?

Show Answer Hide Answer
Correct Answer: B, D, E

Question No. 3

Which entity should you use to configure the manufacturing plant in Functional Manager?

Show Answer Hide Answer
Correct Answer: B

Question No. 4

In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are required to assemble a product. The cost of the assembly is calculated by using the standard costing method. The work definition and resource rates of the assembly have been defined as required.

A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before finally publishing estimates as frozen standards to cost accounting by using a cost planning scenario. While reviewing rolled up costs, the extended costs of purchase components are not included in a rolled-up scenario.

Identify the reason.

Show Answer Hide Answer
Correct Answer: D

Question No. 5

Identify three entities that must be set up in Oracle Manufacturing Cloud to create a Work Definition for an item that will be manufactured in-house.

Show Answer Hide Answer
Correct Answer: A, B, D