Free Oracle 1Z0-1057-22 Exam Actual Questions

The questions for 1Z0-1057-22 were last updated On Sep 18, 2024

Question No. 1

A consulting services company is currently working on a business transformation project for your client, which spans multiple years. At the first period close, the consulting services company has recognized revenue and the accounting entry created is:

Dr Unbilled Receivables 40,000

Cr Revenue 40,000

At the end of the period, the client is sent an associated bill. What would be the corresponding invoice accounting entry? (Choose the best answer.)

Show Answer Hide Answer
Question No. 2

You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. (Choose three.)

Show Answer Hide Answer
Correct Answer: C, D, E

Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapex/define-project-management-configuration.html#OAPEX1357147

Topic - Microsoft Project Prevalidation: Explained

The following table describes Prevalidation rules for tasks and resource assignments.

Level

Rule

Lowest-level tasks

One labor and multiple expense resources are allowed for a lowest-level task. Remove other resources.

Summary tasks

Only one labor resource with zero allocation is allowed for a summary task. Remove all other resources.

Milestone tasks

No subtasks are allowed under milestone tasks. Milestones must be lowest-level tasks.

Milestone tasks

Milestone tasks must have zero duration.

Milestone tasks

Only one labor resource, with zero effort, is allowed for a milestone task. Remove all other resources.

When exporting milestone tasks, ensure that the tasks:

Are lowest-levels task with zero duration, that is, the same start and finish dates.

Have only one labor resource assignment with zero effort.

Have percent work complete values of 0 or 100 percent. Any other values are set to zero before export.


Question No. 3

Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost of each asset. Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)

Show Answer Hide Answer
Correct Answer: C

Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project-foundation-configuration-manage-project-types.html#OAPFM220111

Topic -- Asset Cost Allocation Methods: Explained

The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.

You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.

Projects and project templates inherit a default asset cost allocation method from the associated project type. You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.

The following table describes the available asset cost allocation methods.

Method

Basis of Cost Allocation

Actual Units

Number of units defined for each asset

Current Cost

Construction-in-process (CIP) cost of each asset

Estimated Cost

Estimated cost of each asset

Standard Unit Cost

Combination of the standard unit cost and the number of units defined for each asset

Spread Evenly

Equal allocation of cost to each asset


Question No. 4

Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

Show Answer Hide Answer
Correct Answer: B

Reference https://ppm-help.saas.hpe.com/en/9.42/Help/Content/UG/PjMUG/view_pj_cost_data_costtab.htm

Below is an example of the Financial Summary view on the Cost tab of the Project Overview page.


Question No. 5

Which five steps are required for the File-Based Data Import Integration option?

Show Answer Hide Answer