Free NFPA CWBSP Exam Actual Questions

The questions for CWBSP were last updated On Dec 17, 2024

Question No. 1

Working plans are required to have the total system volume of the system for

Show Answer Hide Answer
Correct Answer: C

Working plans for dry systems are required to include the total system volume, as this information is critical for determining the amount of air or nitrogen needed to pressurize the system and for calculating the time to water delivery. This requirement helps ensure the system's effective operation and quick response in the event of a fire.


Question No. 2

What piping material is acceptable for the suction and discharge piping pressure maintenance pumps?

Show Answer Hide Answer
Correct Answer: B

Black or galvanized steel piping is acceptable for the suction and discharge piping of pressure maintenance (jockey) pumps in fire protection systems. These materials offer the necessary strength and durability for such applications.


Question No. 3

What is the minimum temperature rating of ceiling sprinklers in roll paper stored at 15 ft. (4.6 m) or less?

Show Answer Hide Answer
Correct Answer: C

The minimum temperature rating for ceiling sprinklers in roll paper storage areas that are 15 ft or less in height is typically 150F (66C). This rating is selected to provide a buffer between the ambient temperature conditions and the activation temperature of the sprinklers, preventing accidental activation.


Question No. 4

Using the Hazen-Williams formula, determine the friction loss in 150 ft (45.7 m) of 1 in. (25 mm) black steel schedule

40 pipe, flowing 30 gpm (115 lpm) in a wet system.

Show Answer Hide Answer
Correct Answer: A

Using the Hazen-Williams formula, the friction loss in 150 feet of 1-inch black steel schedule 40 pipe flowing 30 gpm in a wet system would be approximately 27.5 psi. This calculation considers the pipe's material, size, length, and flow rate.


Question No. 5

The minimum flow rate for the required forward flow test of a backflow prevention assembly shall be the

Show Answer Hide Answer
Correct Answer: D

The minimum flow rate for the forward flow test of a backflow prevention assembly should be the system demand plus hose stream allowance, where applicable, to ensure the assembly can handle the maximum expected flow during a fire event.