Free Microsoft MB-335 Exam Actual Questions

The questions for MB-335 were last updated On Jan 15, 2025

Question No. 1

A company uses Dynamics 365 Supply Chain Management for Process manufacturing.

You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.

You need to optimize the planned production orders.

What should you do?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

A company produces generic and name-brand paper plates in the same factory using standard costing and unrig the same Bill of materials and routes to produce both product.

The finance and production teams want a way to new individual raw material consumption costs in the ledger.

You need to add a production group to tie finished good to control postings to the ledger. What should you do?

Show Answer Hide Answer
Correct Answer: C

Question No. 3

You need to configure production control parameters for liquid cleaning solution manufacturing.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Show Answer Hide Answer
Correct Answer: B, C

https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/formulas-versions

Question No. 4

You need to configure the bicycles' production resource.

Which option should you use?

Show Answer Hide Answer
Question No. 5

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear on the review screen.

A manufacturing company produces electronic components and devices.

The company has scheduling issues related to using working time calendars in manufacturing.

You need to ensure that the working time calendar is used when manufacturing jobs are scheduled.

Solution: Enable route groups for a capacity job type.

Does the solution meet the goal?

Show Answer Hide Answer
Correct Answer: B