At ValidExamDumps, we consistently monitor updates to the ISTQB ATM exam questions by ISTQB. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the ISTQB Advanced Test Manager exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by ISTQB in their ISTQB ATM exam. These outdated questions lead to customers failing their ISTQB Advanced Test Manager exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the ISTQB ATM exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

Assume you are managing a test automation project for a mission-critical system. Because vendor provided tools and open source solutions don't meet the needs of this project, you ask your test team to develop a custom automation framework. Which of the following management issues associated to the development of this custom automation framework is least likely to manage?

K2 1 credit

Show Answer Hide Answer
Correct Answer: C

Question No. 2

You are the Test Manager of a project that adopts a V-model with four formal levels of testing.

unit, integration, system and acceptance testing.

On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low-level design and code have been performed prior to testing.

Assume that no requirements defects have been reported after the release of the product. Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness?

K3 2 credits

Show Answer Hide Answer
Correct Answer: A, E

Question No. 3

You are the Test Manager of a new project that will have three formal levels of testing. unit, integration and system testing. The testing strategy you decide to adopt a blend of risk-based testing and reactive testing strategies.

Which of the following answers describes the most consistent example of implementation of this test strategy during the execution of the system tests?

K2 1 credit

Show Answer Hide Answer
Correct Answer: C

Question No. 4

You are performing a quality risk analysis for a CSCI (Computer Software Configuration Item) used to implement a CBIT (Continuous Built-In Test) module of a safety-critical system. During the quality risk analysis you are trying to identify the ways in which failures of the CBIT module can occur, for each of them trying to determine the potential causes and likely effects, and the risk level (calculated as the product of three factors: severity, occurrence and detection). Which of the following risk analysis techniques are you working with? K2 1 credit

Show Answer Hide Answer
Correct Answer: B

Question No. 5

Which of the following statements about management of product quality risks in mature organizations with respect to the lifecycle, is true?

K2 1 credit

Show Answer Hide Answer
Correct Answer: B