A workstation has a FENCE of 10, LIMIT of 5, and a job with a priority of 10 currently on HOLD. What must be changed to enable a job to launch?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

When configuring High Availability for Dynamic Workload Console, which file must be modified to make changes to DBhost and DBport?

Show Answer Hide Answer
Question No. 3

Which object exists independently in the database and can be used in multiple job streams?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

What are the two main object types of event management plug-ins?

Show Answer Hide Answer
Question No. 5

Which two options should be set in order for a job to be flagged as mission-critical?