Free IASSC ICGB Exam Actual Questions

The questions for ICGB were last updated On Nov 18, 2024

Question No. 1

A periodic time frame can be used to arrange for Control Limit and Center Line calculations with good SPC implementation in a process.

Show Answer Hide Answer
Correct Answer: A

Question No. 2

Measurement System Analysis is a procedure used to quantify all ____________ in the method or system used for taking measurements.

Show Answer Hide Answer
Correct Answer: C

Question No. 3

Conducting a viable Capability Analysis using Attribute Data one must obtain a fairly large sample set to be statistically sound.

Show Answer Hide Answer
Correct Answer: A

Question No. 4

Lean focuses on the sequence of activities and work required to produce a product or a service. This flow is called a ___________________.

Show Answer Hide Answer
Correct Answer: C

Question No. 5

Long-term Data represents all the variation that one can expect within the subject process.

Show Answer Hide Answer
Correct Answer: A