Your customer has me following HPE Synergy setup

- Three frames fully populated with HPE Synergy 480 Gen10 Plus modules and 25Gb/s downlink speed formulating a single logical enclosure

- Two HPE Virtual Connect SE 100Gb F32 Module for Synergy

- Four HPE Synergy 50Gb interconnect Link Module

- Six HPE Synergy Virtual Connect SE 32Gb FC Modules

The customer needs to add a frame.

Which statement about the expansion of this setup is true?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

Which statement about HPE OneView milestone releases is true?

Show Answer Hide Answer
Correct Answer: A

Question No. 3

You need to configure a RoCE network to enable lossless networking for HPE J2000 Flash Enclosure support Which interconnects are required to support this connection? (Select two.)

Show Answer Hide Answer
Correct Answer: B, D

Question No. 4

Your customer needs to move an application from an HPE Synergy 480 Gen10 Compute Module to an HPE Synergy 660 Gen 10 Compute Module. The 480 has a switch that has been manually zoned outside of HPE OneView.

What must the customer do before migrating the application?

Show Answer Hide Answer
Correct Answer: C

Question No. 5

Your customer reports mat an external FC boot volume for Windows server is visible four times in the Disk Management 1 online and 3 offline.

What should you do to resolve this issue?