Free GAQM PPM-001 Exam Actual Questions

The questions for PPM-001 were last updated On May 5, 2025

At ValidExamDumps, we consistently monitor updates to the GAQM PPM-001 exam questions by GAQM. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the GAQM Professional in Project Management (PPM) - Standard Package exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by GAQM in their GAQM PPM-001 exam. These outdated questions lead to customers failing their GAQM Professional in Project Management (PPM) - Standard Package exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the GAQM PPM-001 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

While preparing your risk responses, you realize that you have not planned for unknown risk events. You need to make adjustments to the project to compensate for unknown risk events. These adjustments are based on your past project experience when unknown risk events occurred and knocked the project off track. What should you do?

Show Answer Hide Answer
Correct Answer: A

Question No. 2

When does risk monitoring and control occur?

Show Answer Hide Answer
Correct Answer: C

Question No. 3

Lessons learned are most often based upon project historical records. Lessons learned can be used to:

Show Answer Hide Answer
Correct Answer: B

Question No. 4

You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following as part of the risk register update output except which one?

Show Answer Hide Answer
Correct Answer: A

Probability of achieving time and cost estimates is an update that is produced from the Quantitative Risk Analysis process.


Question No. 5

A project manager convenes a meeting to determine why the time to produce one product according to specifications has increased from one day to three days over the past month. Which tool or technique is used in this case?

Show Answer Hide Answer
Correct Answer: D