Free GAQM PPM-001 Exam Actual Questions

The questions for PPM-001 were last updated On Nov 19, 2024

Question No. 1

Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

Lessons learned are most often based upon project historical records. Lessons learned can be used to:

Show Answer Hide Answer
Correct Answer: D

All of the other alternatives apply


Question No. 3

Which of the following is the BEST thing to do at a bidder conference?

Show Answer Hide Answer
Correct Answer: D

Question No. 4

When is a project finished?

Show Answer Hide Answer
Correct Answer: C

Question No. 5

Which of the following equations is used to calculate cost variance?

Show Answer Hide Answer
Correct Answer: A