Free GAQM PPM-001 Exam Actual Questions

The questions for PPM-001 were last updated On Dec 16, 2024

Question No. 1

Reserve Analysis a technique not used in:

Show Answer Hide Answer
Correct Answer: C

Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs.


Question No. 2

You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following as part of the risk register update output except which one?

Show Answer Hide Answer
Correct Answer: A

Probability of achieving time and cost estimates is an update that is produced from the Quantitative Risk Analysis process.


Question No. 3

Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and techniques of what process?

Show Answer Hide Answer
Correct Answer: A

Question No. 4

Which of the following is CORRECT?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

What document should be reviewed by a project manager before finalizing the project closure?

Show Answer Hide Answer
Correct Answer: A