Free GAQM CSM-001 Exam Actual Questions

The questions for CSM-001 were last updated On Dec 16, 2024

Question No. 1

Which level of planning concentrates on the future of the product and its ultimate goal with the possible changes to them and their likelihood?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

Which of the following is a role in the Scrum framework?

Show Answer Hide Answer
Correct Answer: B

Question No. 3

Which system provides evolutionary framework for incremental process improvement?

Show Answer Hide Answer
Correct Answer: A

Question No. 4

The _____________ Team is responsible for delivering potentially shippable product increments at the end of each Sprint.

Show Answer Hide Answer
Correct Answer: A

Question No. 5

What artifact shows actual versus planned progress?

Show Answer Hide Answer
Correct Answer: B