Free GAQM APM-001 Exam Actual Questions

The questions for APM-001 were last updated On Nov 17, 2024

Question No. 1

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

An input to the Control Quality process is:

Show Answer Hide Answer
Correct Answer: D

Question No. 3

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

Show Answer Hide Answer
Correct Answer: D

Question No. 5

An input used in developing the communications management plan is:

Show Answer Hide Answer
Correct Answer: B