Free GAQM APM-001 Exam Actual Questions

The questions for APM-001 were last updated On Jan 16, 2025

Question No. 1

A technique used to determine the cause and degree of difference between baseline and actual performance is:

Show Answer Hide Answer
Correct Answer: B

Question No. 2

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?

Show Answer Hide Answer
Correct Answer: C

Question No. 3

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Show Answer Hide Answer
Correct Answer: D

Question No. 4

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Which of the following documents allows the project manager to assess risks that may require near term action?

Show Answer Hide Answer
Correct Answer: C