Free CompTIA PK0-004 Exam Actual Questions

The questions for PK0-004 were last updated On Apr 6, 2025

At ValidExamDumps, we consistently monitor updates to the CompTIA PK0-004 exam questions by CompTIA. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the CompTIA Project+ exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by CompTIA in their CompTIA PK0-004 exam. These outdated questions lead to customers failing their CompTIA Project+ exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the CompTIA PK0-004 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

The government wants to start a project that will launch a satellite but lacks the appropriate SMEs. Which of the following would be BEST to solicit vendors?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

A project manager decides to release a product one month later, knowing marketing studies have shown doing so could require increased manufacturing capacity. Which of the following risk strategies is being employed?

Show Answer Hide Answer
Correct Answer: B

Question No. 3

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Show Answer Hide Answer
Correct Answer: A

Question No. 4

A project sponsor has requested documentation to determine the scheduled activities for a project that is

running behind schedule. Which of the following documents should the project manager send to the sponsor to

quickly identify the project activities?

Show Answer Hide Answer
Correct Answer: D

Question No. 5

A project has passed a phase-gate, and the new phase is ready to begin. Which of the following is the MOST appropriate method to communicate the transition to team?

Show Answer Hide Answer
Correct Answer: B