Free Certinia PSA-Sysadmin Exam Actual Questions

The questions for PSA-Sysadmin were last updated On Jan 17, 2025

Question No. 1

You have set up a Flow to automatically assign a resource's manager to the approver field on Timecards. Users have reported that submitted Timecards are going to the Project Manager for approval and not the resource's manager. Of the following, which could be a reason for this?

Show Answer Hide Answer
Correct Answer: A

Question No. 2

Your company has both full time and part time resources. From a Human Resources perspective, part time resources can work any number of hours per week. From a Resource Planning perspective, management has agreed that part time workers can be estimated at 20 hours per week.

Based on this information, how many work calendars should be created?

Show Answer Hide Answer
Correct Answer: C

Question No. 3

One of the Project Managers in your company has reached out to you to resolve an issue. Many of the Timecards that were approved in the last week against projects are not reflecting back on the Project Actuals.

You check that the Actuals Configuration Group > Calculation Mode option is set to "Scheduled".

What is the next step you should take?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

When setting up a Utilization calculation, what does the "Is Report Master" field mean?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Your company's leadership noticed that the "PSA Resourcing" Lightning Component is displaying a "Default Cost Rate" column. They asked you to remove this column from the component. You edited the Resource Request Lightning Page, selected the "PSA Resourcing" component, and identified the "Column Field Set" setting.

What is the next step to complete this change?

Show Answer Hide Answer
Correct Answer: A