At ValidExamDumps, we consistently monitor updates to the BICSI RCDDv14 exam questions by BICSI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the BICSI Registered Communications Distribution Designer (RCDD) exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by BICSI in their BICSI RCDDv14 exam. These outdated questions lead to customers failing their BICSI Registered Communications Distribution Designer (RCDD) exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the BICSI RCDDv14 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

While setting up a program's infrastructure and plan, a program management team develops documents and processes that provide commonality and consistency throughout the program's components. What should the team also prepare, if not already provided by the organization's assets?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years

What is the expected time of delivery?

Show Answer Hide Answer
Correct Answer: A

Question No. 3

A municipal agency manages a city's water and wastewater infrastructure. A regulation requires the replacement of sewer lines throughout the city at a cost of US$2 billion over 30 years

The city has been managing this program with various program teams, and has a project controls office In place to track protects separate from the program management team A program manager is hired to standardize all deliverables from component projects under the program.

What should the program manager do next?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

The program director of a four-year program, estimated to require 600.000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the last phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation

Which of the following metrics should the PMO capture on a monthly basis?

Show Answer Hide Answer
Correct Answer: B