Free BICSI RCDDv14 Exam Actual Questions

The questions for RCDDv14 were last updated On Nov 4, 2024

Question No. 1

In a transformational program, all projects are on track and delivering their objective. However stakeholders are hesitant to take on the new processes because performance in the current environment may not be representative of actual performance Stakeholders fear that the program will fail to provide the service required.

To assure positive performance in the current environment, the program manager should do which of the following?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

Show Answer Hide Answer
Correct Answer: D

Question No. 3

A program manager has four projects pending approval Senior management asks the program manager to identity a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision.

Which project should the program manager select to be cancelled?

Show Answer Hide Answer
Correct Answer: D

Question No. 4

A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified

Key stakeholders for the program should include which of the following?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.

In this situation, what should the program manager change about the risk management plan?

Show Answer Hide Answer
Correct Answer: B