Free BCS RE18 Exam Actual Questions

The questions for RE18 were last updated On Nov 19, 2024

Question No. 1

A business analyst has interviewed project stakeholders and has a robust list of requirements.

At which stages in the requirements engineering framework would he check that these requirements support the business objectives defined at the start of the project?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

A set of requirements for a new online health information portal have been prioritized using

MoSCoW:

REQ#1: (S)

REQ#2: (C)

REQ#3: (S)

REQ#4: (M)

REQ#5: (M)

REQ#6: (C)

REQ#7: (W)

Only the minimum usable subset was approved for inclusion in the first iteration of the project. After the build for the first iteration began, it was estimated there was enough time to add two additional requirements, without negative impact on the project schedule.

Which two requirements will now be added to the first iteration build?

Show Answer Hide Answer
Correct Answer: A

Question No. 3

Life Extenders is a not-for-profit organization, which renovates donated furniture to sell in its high street shop; any profit it makes is given to local charities. The operations director is planning a small project to implement a website to support the organization.

The business analyst assigned to work on this project is in the process of identifying stakeholder roles. The following have been suggested:

A) Members of the public could be customers of Life Extenders.

B) Members of the public could be suppliers of Life Extenders.

C) Life Extenders is a partner of other local charities.

D) Life Extenders is a regulator as it is a not-for-profit organization.

Which of these statements are correct?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'.

What element of requirements management will offer this?

Show Answer Hide Answer
Correct Answer: A

Change controlis a systematic approach to managing allchangesmade to a product or system. The purpose is to ensure that no unnecessarychangesare made, that allchangesare documented, that services are not unnecessarily disrupted and that resources are used efficiently.


Question No. 5

A business analyst working on a project has identified:

3 requirements for which there is a workaround and the users can live without;

2 requirements that the users can live without for now;

15 requirements which, if not delivered, will make the solution unworkable or useless.

When these requirements are prioritized using MoSCoW, which of the following categories will not be

used?

Show Answer Hide Answer