Free BCS ISEB-PM1 Exam Actual Questions

The questions for ISEB-PM1 were last updated On Nov 3, 2024

Question No. 1

You have assembled your thoughts into a message. As you pass this information to a second party, you are giving this person your:

Show Answer Hide Answer
Correct Answer: D

Question No. 2

Quality and credibility of the qualitative risk analysis process requires that different levels of the risk's probabilities and impacts be defined is the definition of what?

Show Answer Hide Answer
Correct Answer: B

Question No. 3

What quality control tool graphically represents how various elements of a system interrelate?

Show Answer Hide Answer
Correct Answer: B

Question No. 4

What is the definition of project plan execution?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

The most rapid Estimate Costs technique is:

Show Answer Hide Answer
Correct Answer: C

Computerized estimating rapid Estimate Costs technique