Free BCS ISEB-PM1 Exam Actual Questions

The questions for ISEB-PM1 were last updated On Nov 19, 2024

Question No. 1

A work breakdown structure is most useful for:

Show Answer Hide Answer
Correct Answer: E

Question No. 2

Resource reallocation from non critical to critical activities is an example of which

Project Scheduling technique:

Show Answer Hide Answer
Correct Answer: C

Resource Leveling: Allocate scare resources to critical path activities first.


Question No. 3

In crashing a task, you would focus on:

Show Answer Hide Answer
Correct Answer: D

Question No. 4

Earned value measurement is an example of:

Show Answer Hide Answer
Correct Answer: A

Question No. 5

What should a project manager do with low-priority risks?

Show Answer Hide Answer
Correct Answer: B