Free BCS ISEB-PM1 Exam Actual Questions

The questions for ISEB-PM1 were last updated On Dec 18, 2024

Question No. 1

When can pre-assignment of project team members occur?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

The most rapid Estimate Costs technique is:

Show Answer Hide Answer
Correct Answer: C

Computerized estimating rapid Estimate Costs technique


Question No. 3

Which of the following is an output of the Estimate Activity Resources process?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

Employee unions would most likely satisfy which level in Maslow's hierarchy of needs?

Show Answer Hide Answer
Correct Answer: C

Question No. 5

The work that must be done in order to deliver a product with the specified features and functions is:

Show Answer Hide Answer
Correct Answer: B

Project Scope: The work that must be done in order to deliver a product with the specified features

and functions.