Free APM APM-PFQ Exam Actual Questions

The questions for APM-PFQ were last updated On Jan 17, 2025

Question No. 1

When in the project life cycle might analogous estimating be most commonly used?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

What is a likely benefit of re-estimating throughout the project life cycle?

Show Answer Hide Answer
Correct Answer: D

Question No. 3

Which of the following is an activity in a typical change control process?

Show Answer Hide Answer
Correct Answer: A

Question No. 4

What is the most likely result of providing effective quality management in the project?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

Which of these is a key aspect of Programme Management?

Show Answer Hide Answer
Correct Answer: C