Free APM APM-PFQ Exam Actual Questions

The questions for APM-PFQ were last updated On Dec 17, 2024

Question No. 1

Which stakeholders are likely to form the main part of a project governance board?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

Which of these is likely to occur if the scope is poorly defined?

1. Additional time spent in the concept phase

2. Scope creep

3. Budget over/under runs

4. Scheduling problems

Show Answer Hide Answer
Correct Answer: D

Question No. 3

Which of these is a correct definition of an Estimate?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

What might be considered a disadvantage of virtual communication?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

Which of the following aspects would best describe part of the project environment?

Show Answer Hide Answer
Correct Answer: C