Free APICS CPIM Exam Actual Questions

The questions for CPIM were last updated On Nov 20, 2024

Question No. 1

The old saying ''What you do not measure, you cannot control'', is as valid today as it was when first stated. The necessary step/s in implementing a successful performance measurement program is/are:

Show Answer Hide Answer
Correct Answer: D

Question No. 2

The material requirement plan authorizes production activity control (PAC):

Show Answer Hide Answer
Correct Answer: D

Question No. 3

When the last operation is on the routing is scheduled first and is scheduled for complete at the due date, this is called:

Show Answer Hide Answer
Correct Answer: D

Question No. 4

The objective of the MRP is to have:

Show Answer Hide Answer
Correct Answer: D

Question No. 5

The quantity on hand plus the quantity ordered must equal the sum of the demand during the lead time plus the demand during the review period plus safety stock.

Show Answer Hide Answer
Correct Answer: A