Free Adobe AD0-E903 Exam Actual Questions

The questions for AD0-E903 were last updated On Feb 21, 2025

At ValidExamDumps, we consistently monitor updates to the Adobe AD0-E903 exam questions by Adobe. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the Adobe Workfront Project Manager Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by Adobe in their Adobe AD0-E903 exam. These outdated questions lead to customers failing their Adobe Workfront Project Manager Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the Adobe AD0-E903 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

Show Answer Hide Answer
Correct Answer: A

The Projected Date in Adobe Workfront is dynamically calculated based on the progress of the task, any task constraints, and its dependencies. This date provides a more accurate reflection of when a task is likely to be completed, considering the current progress and any updates to predecessor tasks. On the other hand, the Planned Date refers to the originally scheduled completion date, and the Estimated Date is not manually entered but inferred from system calculations.


Question No. 2

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

Show Answer Hide Answer
Correct Answer: A

In Workfront, creating a program-specific dashboard allows for the presentation of real-time data to stakeholders. Additionally, automated reports can be set to send out weekly, meeting the requirement for a consistent recap. This automation reduces the manual effort of downloading and sending reports each week.


Question No. 3

How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

Show Answer Hide Answer
Correct Answer: C

To create a custom report in Workfront that focuses on issues logged to projects, the project manager needs to create a new Issue report from the Reports page. By applying a filter based on the Project Owner ID and grouping the report by project name, they can track all the issues associated with the projects they own. This approach provides clear visibility into project-related issues.


Question No. 4

A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.

How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

Show Answer Hide Answer
Correct Answer: C

In Workfront, when adjusting user access, it's important to ensure that Program Manager A only has the necessary level of access to their own program. To rectify the over-access issue, the portfolio manager must share the relevant program with Program Manager A with the correct Manage access and remove their broader Manage access to the portfolio. This restricts their control to only their specific program.


Question No. 5

An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?

Show Answer Hide Answer
Correct Answer: C

In Workfront, custom data fields created for projects are typically found within the 'Business Case' section, specifically under 'Project Info.' This area houses key project information and unique custom fields that are relevant to the project's setup. The 'Project Details' section is more focused on task-related information and the overall summary of the project.