Free Adobe AD0-E903 Exam Actual Questions

The questions for AD0-E903 were last updated On Nov 17, 2024

Question No. 1

A team lead wants to see all hours that have been logged this month by members of the team lead's home team, organized by project. How should the team lead create this view?

Show Answer Hide Answer
Correct Answer: B

The team lead should create a report in the Reports area to see all hours logged by the home team during the current month. By using filters for Home Team ID and Entry Date, and grouping the results by Project Name, the team lead can view hours logged in a project-based format for the entire home team during the selected time period.


Question No. 2

Which wildcard should be used on a project report when filtering for projects that have a planned completion date greater than 1 month from the current date?

Show Answer Hide Answer
Correct Answer: C

In Adobe Workfront, the correct wildcard to filter for a project completion date greater than 1 month from the current date is CURRENTDATE + 4w. This wildcard ensures that the filter captures projects scheduled to be completed more than four weeks (or one month) from the current day. Workfront uses such wildcards for dynamic date filtering in reports.


Question No. 3

A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.

How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

Show Answer Hide Answer
Correct Answer: C

In Workfront, when adjusting user access, it's important to ensure that Program Manager A only has the necessary level of access to their own program. To rectify the over-access issue, the portfolio manager must share the relevant program with Program Manager A with the correct Manage access and remove their broader Manage access to the portfolio. This restricts their control to only their specific program.


Question No. 4

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

Show Answer Hide Answer
Correct Answer: C

In Workfront, if a task that is part of the critical path is delayed, it affects the overall project schedule. Even though the task is not overdue yet, Workfront's automated system flags the project as 'At Risk' if there is a delay in progress that could impact the project's timeline. This 'At Risk' condition acts as a warning to project managers and stakeholders that immediate attention is needed.


Question No. 5

A team lead needs to regularly report on the adherence of budget and timeline of a group of projects.

What should the team lead use to organize these projects to allow them to be tracked together?

Show Answer Hide Answer
Correct Answer: B

In Workfront, a 'Program' is used to group related projects that share a common objective or need to be tracked together, such as adherence to budget and timeline. Programs allow for collective reporting on these projects, making it easier for team leads to monitor progress, manage resources, and report on key performance indicators (KPIs) across multiple projects.