Free Adobe AD0-E903 Exam Actual Questions

The questions for AD0-E903 were last updated On Dec 20, 2024

Question No. 1

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

Show Answer Hide Answer
Correct Answer: C

To view the Budgeted Variances between the planned and actual hours for the current week, the project manager should navigate to the Finance section of the project. This section provides detailed financial information, including cost and hour variances, which help track how actual project performance compares to the initial budget and plan. The Hours tab typically displays the logged hours, while the Utilization section is more focused on resource usage and allocation.


Question No. 2

An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.

In which project area does this information reside?

Show Answer Hide Answer
Correct Answer: B

Adobe Workfront, information about the Group and Portfolio assigned to a project is stored in the 'Project Details' section. This section contains the overall information regarding a project, such as the Portfolio it belongs to and the Group responsible for it. The 'Queue Details' section pertains to request queues, while 'Metrics' generally involves the measurement and tracking of key performance indicators but not specific data like Group and Portfolio.


Question No. 3

Which project Condition is set when the Progress Status of the project is Behind or At Risk?

Show Answer Hide Answer
Correct Answer: B

In Adobe Workfront, when a project's progress status is marked as Behind or At Risk, the project condition is set to At Risk. This indicates that the project may not meet its deadline or performance metrics, signaling to the project team and stakeholders that corrective action may be necessary. The 'In Trouble' status is reserved for more severe cases, and 'Late' is generally used for tasks or projects that have passed their planned completion dates without being finished.

The At Risk status allows proactive intervention to address potential issues before they escalate into bigger problems.


Question No. 4

Refer to the exhibit.

What do the connector lines between tasks in a Gantt chart represent?

Show Answer Hide Answer
Correct Answer: C

In Workfront, the connector lines in a Gantt chart represent the predecessor relationships between tasks. These lines show how one task depends on another, indicating the order in which tasks need to be completed. This helps project managers visualize task dependencies and how changes in one task can affect others in the timeline.


Question No. 5

A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.

What should the project manager ask users to do when it comes to completing tasks?

Show Answer Hide Answer
Correct Answer: B

In scenarios where multiple individuals are assigned to a task, Workfront allows each user to mark the task as 'Done with my part' to signify their portion of the task is complete. This ensures that progress is tracked for each user, and the task is only marked as complete when all assigned users have finished their work.