Free Adobe AD0-E903 Exam Actual Questions

The questions for AD0-E903 were last updated On Sep 17, 2024

Question No. 1

Which wildcard should be used on a project report when filtering for projects that have a planned completion date greater than 1 month from the current date?

Show Answer Hide Answer
Correct Answer: C

In Adobe Workfront, the correct wildcard to filter for a project completion date greater than 1 month from the current date is CURRENTDATE + 4w. This wildcard ensures that the filter captures projects scheduled to be completed more than four weeks (or one month) from the current day. Workfront uses such wildcards for dynamic date filtering in reports.


Question No. 2

A project manager has been asked to create a report showing the planned completion date for all the project manager's projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

Show Answer Hide Answer
Correct Answer: A

To create a report that meets the specifications, the project manager should create a new report from the Reports page, filter by Project Owner ID, and add a column for Planned Completion Date. Setting the default view to Calendar View and using the Color ID field to assign the color purple ensures that all the manager's projects are visible in the desired format and color.


Question No. 3

A team lead wants to see all hours that have been logged this month by members of the team lead's home team, organized by project. How should the team lead create this view?

Show Answer Hide Answer
Correct Answer: B

The team lead should create a report in the Reports area to see all hours logged by the home team during the current month. By using filters for Home Team ID and Entry Date, and grouping the results by Project Name, the team lead can view hours logged in a project-based format for the entire home team during the selected time period.


Question No. 4

Which wildcard should be used in a task report when using an Assigned To filter to show the logged-in user all tasks to which she is assigned as the primary task owner?

Show Answer Hide Answer
Correct Answer: B

To create a task report that shows the logged-in user all tasks they are assigned to as the primary task owner, USER.ID is the correct wildcard. USER.ID dynamically filters tasks based on the unique identification of the logged-in user, ensuring that only tasks assigned to them are displayed. USER.NAME would not uniquely identify the logged-in user, and USER.roleID is related to roles rather than task assignments.


Question No. 5

All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?

Show Answer Hide Answer
Correct Answer: C

Even if the task shows 100% complete, the Status of the task may still be listed as something other than 'Done.' Workfront requires that both the Status and the Percent Complete indicate the task is fully completed before the project can be marked as complete. The Project Owner can filter for tasks that are not marked as 'Done' and update their statuses accordingly.