Free AACE International AACE-PSP Exam Actual Questions

The questions for AACE-PSP were last updated On Mar 31, 2025

At ValidExamDumps, we consistently monitor updates to the AACE International AACE-PSP exam questions by AACE International. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the AACE International Planning & Scheduling Professional (PSP) Exam exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by AACE International in their AACE International AACE-PSP exam. These outdated questions lead to customers failing their AACE International Planning & Scheduling Professional (PSP) Exam exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the AACE International AACE-PSP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

Which of the following statements is true?

Show Answer Hide Answer
Correct Answer: A

Question No. 3

In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

If all other work proceeds according to the Baseline plan, how many times will the critical path change?

Show Answer Hide Answer
Correct Answer: C

Question No. 5

Estimate to complete (ETC) is __________________.

Show Answer Hide Answer
Correct Answer: A