Free AACE International AACE-PSP Exam Actual Questions

The questions for AACE-PSP were last updated On Jan 17, 2025

Question No. 1

Which statement is true?

Show Answer Hide Answer
Correct Answer: A

Question No. 2

Determine the correct formula and date for the late start for the Activity 11001:

Show Answer Hide Answer
Correct Answer: A

Question No. 3

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

Show Answer Hide Answer
Correct Answer: C