Free AACE International AACE-PSP Exam Actual Questions

The questions for AACE-PSP were last updated On Apr 23, 2025

At ValidExamDumps, we consistently monitor updates to the AACE International AACE-PSP exam questions by AACE International. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the AACE International Planning & Scheduling Professional (PSP) Exam exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by AACE International in their AACE International AACE-PSP exam. These outdated questions lead to customers failing their AACE International Planning & Scheduling Professional (PSP) Exam exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the AACE International AACE-PSP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

Show Answer Hide Answer
Correct Answer: A

Question No. 2

Which of the following is NOT required when performing weekly or monthly schedule updates?

Show Answer Hide Answer
Correct Answer: D

Question No. 3

For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Project schedules help control all of the following EXCEPT for_____________________.

Show Answer Hide Answer
Correct Answer: A